Sequencing, snagging and site safety, from the people on site.

Trades, supervisors and site managers each see a different part of the job. Ask all of them, and see where it breaks.

What comes back

From 28 conversations to a sop and a ranked report

28
People asked
5
Languages
6
Days
The interviewAI

On your last second fix, what was still unfinished when you arrived?

Plastering wasn't done in two rooms, so we left the faceplates off and came back a week later.

Electrician, 8 years

Who told you the rooms were ready that day?

On their phone or laptop, talking or typing, in their own language.

SOPFrom 20 people

Second fix sequence

  1. 01Confirm plastering is signed off per room
  2. 02Book second fix only after the sign-off
  3. 03Share the sequence with every trade weekly
  4. 04Snag each room before the trade leaves

Written from what people said, in their words. You check it and share it.

What goes wrongRanked
  1. Trades arrive before the last trade has finished

    17 of 28
  2. Site plan order differs from what trades do

    13 of 28
  3. Snags found after the trade has left site

    9 of 28

“The plan says one order. The trades work to another.”

Site supervisor

Example

Two trips for the faceplates

  1. Second fix

    The electricians arrive before the plasterers have finished.

  2. A week later

    A second trip to fit the faceplates.

  3. In the interviews

    The site plan says one order; the trades follow another.

What changed

One sequence per site, kept by the site manager and shared with every trade.